CPPA Bleaching Committee
Mill Opportunities Session, May 2/95
Celgar Castlegar
ISO 9002 Jan 1995
recover more pin chips, so higher wood recovery
9 day s/d - 2 floating roofs installed, cut vent losses by 90%
installed filters for acid to ClO2 plant
digester wash circulation screen modification
Crestbrook
- asset renewal project about $260 million almost complete
- record month for April (675 tpd vs. previous record of 635 tpd), record daily production of 799 ADtpd.
Stora Forest
- building activated sludge effluent treatment - Sept/95
- water conservation projects to reduce load on clarifier
- sulfite mill, 25-30% TCF, every year regrout bottom of Do tower
- 26 day s/d to rebuild generating bank on recovery boiler
Weldwood Hinton
- new Corrudec III on D2 washer
- Do control instrumentation rebuilt
- R8 new barometric condenser
- oxygen delignification control strategy Mar/95
- continuing extended AQ trial
James Maclaren - Thurso
- secondary treatment - Jun/95
- certified ISO 9002 - May/95
- replaced 2 brownstock primary screens with "stingrays" from .014" to .006", shive problem gone, 92% quality to 99%
- 2 brownstock washers converted to Corudec
- CO2 trial brownstock washers - May/95
- 300 t blow tank, separate hw/sw cooking, species segregation
- AQ used regularly to debottleneck liquor cycle
Champion Pensacola
- R3 to R8/R10 - Apr/95
- ECF production, both hw and sw - Jun/95
Weyerhauser Kamloops
- started new digester Oct/94, great startup curve
- "diamond back" chip bin (no moving parts) works great
- EMCC until recently, now low solids cooking (LSC)
- sawdust line uses AQ, kappa number variation reduction (25 kappa), EA down, apparent yield increase
Weyerhauser Prince Albert
- Installing floating roofs on both ClO2 storages
- switched from 10 micron to 1 micron filters
- kajaani ClO2 analyzer for absorption tower
- installed 200 hp motor to p40 pump, will increase recirculating rate, linear velocity is close to 9 ft/sec
- enzymes since fall/92 IOGEN GS35, now HS70, less expensive
- fall/94 upgraded digester DCS
- permanent brown screen room acidification is under construction
- purchased Kajaani kappa analyzer
Fletcher Challenge Canada Mackenzie
- installed chip truck dump, start up Apr/95
- new Fisher Provox DCS system installed in recaust fall/94
- new slaker, causticizers going in 1995
- new thickness screens going in 1995
- AQ trial - tentative yield at 3% on BD wood, Kno Standard deviation down from 2.5 to 1.5, all strength tests (viscosity, tear, tensile, burst) higher
- planning to build an M&D sawdust digester, 225 tpd, startup Nov/96, will campaign sawdust and chip pulp through bleach plant and machine
Fletcher Challenge Canada Elk Falls
- Mar 95 ECF mill
- almost finished installing CO2 for sawdust line
- new M&D sawdust digester proposal is being evaluated
- plan AQ trials
Fletcher Challenge Canada Crofton
- finishing modifying sawdust kamyr
- Eop bleaching to B bleach (used in A bleach for last 1.5 years)
- discontinued TCF bleaching
- have floating roofs on ClO2 storage, so run at 13 gpl
- acid filters on R8
- methanol storage taken offline because of rust in nylon gears of pump, found rust was not from tank corrosion, ran straight from a truck during shutdown (Quadra looking into with Methanex)
- added 15% capacity to flakt by improving the steam supply
- achieved 1991 modernization tonnage targets
Canfor Prince George
- both mills (PG Pulp and Intercon) running well, safety record excellent, 99% on grade, quality excellent
- have dropped low AOX ECF grades, all semi-bleach now produced at PG mill
- will trial bleached paper on sack kraft machine, if it works will split bleach plant so can run bleached paper during semi bleach runs
- co-gen plant, medium density fibreboard (MDF) plant in planning stages
- a liquor line will join the two mills together this year
- third ISO 9001 audit will be held Jul/95
St. Laurent La Tuque
- ISO 9002 - Dec/95
- Secondary activated sludge effluent treatment - Sep/95
- installed top former on bleached board machine
- plan to add O2 delig, bs washer (800 Adtpd), new bleachery for sawdust
- convert kamyr chip to sawdust (already have 800 t sawdust on two kamyrs), expect sawdust to be in short supply due to MDF plant startups
Avenor Dryden
- Kajaani kappa analyzer, brightness and residual sensors Do and D1
- new lime mud filter
- 13 gpl in ClO2 storage, doubling storage from 4 hrs to 8
- starting to build new chip handling system
- purchasing new DCS digester, recaust
- fall/94 rebuilt recovery boiler
- MODO "Mops" data archival system
- production record: 28968 Adt slush Mar/95
Avenor Thunder Bay
- hw chip dumper and pad, reclaim system, air density separator, bar thickness screens, chip conditioner - end of 1995
- BMH chip bin, 30 min retention in HW line - June/95
- upgrading A sw pulp machine: new headbox, two new top felts, new cutter, layboy, and new CD controls, expect 65 tpd increase - by Oct/95
- B hw machine third press top felt - May/95
- B evaps O2 SBL oxidation (THR from Air Products) Sep/95
- Secondary effluent for newsmill - end of 1995
- DCS for digesters and bleach plant - 95-96
- commissioning one Kajaani kappa analyzer for both lines
- ISO 9002 - Jul/94
- R10 upgrade from 50 tpd to 60 tpd
- deinking slowed to 40% due to price of recycle fibre, replaced with groundwood
- safety - safest mill in Canada for 1994,
- production record 1994 - 501,000 t slush
Cariboo Quesnel
- successful trial on EA analyzer (Paprican)
- two tube leaks down for 15 days, installed risers, stabilizers to improve circulation
- chip thickness screening may be approved
Western Pulp Squamish
- new Eop tower by Kvaerner, expect AOX<1 kg/t, offload generator so can make ECF
- starting Hazop on chemical storages, finish by this fall (because of ClO2 spill at Powell River)
- new ClO2 analyzer being evaluated, Spectra-Tech, $5000
Northwood Prince George
- AQ pulping is a success, definitely get 1.5-2% off machine, now have contract for two years AQ supply
- alum replaced by Diachem NIAD for water treatment
- trial inline sensor (like ORP) on R8 recirculation loop, reasonable correlation to chlorate concentration, will report in future
- converting B digester to low solids cooking (LSC)
- capital approved to close chip screens to 7mm, Acrowood diamond roll + Rader chip conditioner (chips fall between two rolls that create fissures, reducing effective thickness - replaces slicer) - fall/95
- A line washing upgrade approved - pressure diffuser, mini-O2 (25% delig), post O2 wash press, MC Do, countercurrent filtrate to recovery (brown screens will be closed - presently sewering filtrate) - fall/96
Stone Container Portage Du Fort
- Feb/95 opened new landfill site
- secondary treatment energy conservation
- 94 new production record, new quality record
- 95 well ahead of safety record
- ClO2 storage upgrade to 8 hours - MoE wanted dikes around storage, but too much of a safety hazard, so no new dike. (Celgar has dikes around every storage tank)
EB Eddy Espanola
- in middle of conversion of 15 tpd R3 to 38 tpd R8/R10 - May/95
- Bailey process control view stations and Infi90 DCS upgrade
- Kemotron in recaust this year
- using combination of filtrates from hw and sw extraction stages and 2nd post O2 washer on sw line for ClO2 scrubbing. Old sour water system was 50-80% efficient, alkaline filtrates are 100% efficient. Using Kinney strainer for fibre removal - has ss filter elements (delrin disk did not last 2 months due to temperature)
- conversion of DcEHD bleach lines to DoEDnD - Sep/95
Donohue St. Felicien
- Jan-Feb/95 AQ trial
- dispersant trial since Mar/95, still working on results
- Kajaani kappa analyzer on blow line - Sep/95
- Corudec bs washer - May/95
- liquor cycle size increase, so new slaker, causticizer, lime mud filter, tertiary air to recovery boiler
- CO2 trial bs washers - May/95
- Cogen project starting Sept/95
Alberta Pacific Boyle
- Production records: HW 1930 tpd, SW 1500 tpd
- pitch dispersant trial to replace talc in brownstock area almost complete, will look at replacing talc in bleach plant with detackifier - Reason: due to higher price, and have seen some felt filling from talc
- post O2 delignification pH probe to be installed, no optimization done yet
- upgrading bs washer blower to get consistency up, will do similar trial in bp
- justified installing additional vacuum box on machine
- completed R8 generator trial 13-14 gpl, no increase in emissions from floating roofs, but simulating summer conditions (8C okay, 9C not) had some slippage through absorber. Mill normally 10-11 gpl.
Repap Miramichi
- installed #6 LPF gave 40 - 50 tpd increase
- investigating LSC and side to side switching on digester
- completed 3 surfactant trials with AQ - no conclusions yet
- doing Eop optimization
- during rail strike ran 75% ClO2 substitution
- CO2 trial - Jun/95
- both papermills recently certified ISO 9002
- looking at chip thickness screening
- installing activated sludge for groundwood effluent
James River Marathon
- Secondary treatment 4.5 km away from mill - startup Dec/95
- BS washers coverted to Impco Coru-dek III, have found reduced BL carryover (half), reduced defoamer usage with a cheaper defoamer being used
- Received ISO 9002 certification - Jan/95
- Site optimization study to increase to 660 tpd (RB limited) - new MEEs, feedwater system, pulp m/c rebuild, etc
- new Fisher Provox DCS for batch digesters - startup Sept/95
- R8 reboiler being replaced with titanium grade 7 (currently 22 of 130 tubes are plugged in grade 12 titanium reboiler in service since Nov/89)
Harmac Pacific Nanaimo
- installing floating roofs - May/95
- installing dilute H2SO4 for bleach plant pH control - July/95
- C bleach plant - will reconfigure Papricycle to bleach plant pre-washer and MC Do stage, will run ECF all the time on all 3 bleach plants - fall/95
- new steam and recovery boiler island - new RB, and TG, plus conversion of existing RB to fluidized bed PB - anticipate approval in next few months
- targeting ISO 9001 Sep/95
Sterling Pulp Chemicals
- board approval for 100,000 t/yr chlorate facility in south eastern US, probably Georgia
- debottlenecking existing facilities for 20,000 - 30,000 t/yr extra
Histed Consulting L’Orignal
- TAPPI monograph hypo chapter, water use chapter
- lots of work for consultants
ICI
- closed site at Cornwall
- safety record 32 years 5 million man-hours
Alcell Miramichi
- looking forward to having committee in Sept
- have purchased a 5 tpd bleach plant
Degussa
- are building a new 80,000 tonne peroxide plant near Montreal, startup late 1996
- currently building a tank farm at Montreal site that will receive deep sea shipments of peroxide from Europe and Mobile
Canadian Oxy
- CanadianOxy Chemicals and OxyChem US formed a partnership May 1, 1995 called CXY Chemicals. CXY Chemicals’ assets will include the 4 CanOxy sodium chlorate and one CanOxy chlorine and caustic plant plus OxyChem’s 125,000 ton/year Taft, Louisiana, sodium chlorate plant.