Alcell, Atholville
- starting up $45 million, 60% to secondary treatment
- starting up ECF hw, switching to TCF if they can find peroxide
Avenor, Dryden
- new chip handling system (CTS), commission next summer
- DCS for kiln and digester ; bleach plant and pulp machine year after
- 500,000 manhours safe working, accident, then another 500,000 manhours safe
- purchased kappa analyzer, in process of installing
- starting towards ISO 9002 certification
Avenor, Thunder Bay
- installed BMH chip bin in B Mill
- installed Kajaani Kappa analyzer
Canfor, Prince George
- working on cogeneration project; also medium density fiberboard plant
- installing liquor line between mills; stock line being considered for next year
- will have bleach plant split 10-20% of time
- getting into bleached sack market
- dispersed technical group into mill, all persons working with production, benefits tremendous
- looking at ISO 14000
- one year lost time injury free at Intercon Mill, nine months at PG Milll; very proud of this record
Crestbrook
- maintenance shutdown June 96, made changes to digester, new trim screens, outlet device, ability to add WL to steaming vessel for scale control
- found tube leaks in economizer, shut down 36 hours early
- June/95 ISO 9002 certification
- production records for July and August
- looking at environmental management system
Domtar, Cornwall
- DCS on digester
- converting ClO2 plant to Solvay from Mathieson process
- installing heat exchanger on ClO2 to reduce chilling requirement, energy in bleach plant
Fletcher Challenge Canada, Crofton
- #2 pulp machine wetend upgrade
- #2 kamyr pin chip digester upgrade (DCS, cold blow, stock handling)
- continued reliability work on R8
- 12.5 gpl ClO2 being produced
- looking into purchasing kappa analyzer for kappa factor control
- investigating use of precipitator catch and mud slurry for green liquor polymer replacement
- investigating lump breaker for kilns
- set an August production record
- looking into AQ and polysulphide trial
Fletcher Challenge Canada, Elk Falls
- installing M&D digester June,1996
- installing new trash screen
- making modifications to chemiwasher
Fletcher Challenge Canada, Mackenzie
- construction started on $57 million sawdust digester, 225 tpd, startup Nov/96
- completed first truck dump, installing new weigh scale
- proposing new chip screening system
- audited to ISO 9001-1994, considering on-line document control
- started work on ISO 14000 Environmental Management System
Fraser, Edmunston
- installing DCS in digester Oct 95; standard deviation to go from 3.5 to 2.0
- Cogen boiler startup planned for end of 96
- study to expand mill from 550 to 750 t, then 950 t, construction phase 1 starts May 96, 23 months schedule
- no production increase required on ClO2 generator
- adding O2 delignification with Mg base
- finished installing pin chip recovery system - saving 7 t/d for digester
- installing hog boiler electrostatic precipitator by end of 95
- set production record of 618 t/d daily; make 500 t/d monthly
Harmac Pacific, Nanaimo
- starting up Do pH control system using sulphuric acid; startup Sep 95
- reconfiguring C bleach plant, giving up Papricycle for a bleach pre-washer Oct 95; will be ECF fulltime
- MgSO4 system spring/96
- expect appproval for improved A bleach plant scrubbing Spring/96
- looking at chip thickness screening 90 units/hr, expecting approval to start Nov 95
- working on proposal for new Steam and Recovery island, 1 RB, old RB to PB, install TG 35 MW $225, s/d 2 rb, 4 pb; possible approval Nov 95
- planning for 1996 mini O2 for C bleach plant, similar to B bleach plant system 2 yrs ago
Howe Sound Pulp and Paper, Port Mellon
- ordered Corrudec drum to replace Do washer
- started bar chip thickness screening (recent disc screens did not work well), so far hasn’t helped
- considering an AQ trial next year
- considering a 500 t storage tank so newsmill can use slush, not dried pulp
- looking at pulp machine scanner
Irving, St. John
- DCS on digester, DCS on ClO2 generator plant, DCS with advanced controls in the bleach plant
- construction underway on new 800 tonne bleached high density, new knotters, screening, washing, MC O2 delignification and post washing
- new evaporator, steam stripping of foul condensates,limekiln upgrade - environmentally driven
- complete by May/96
- expecting further announcements
James River, Marathon
- finishing secondary treatment Nov 95; 4.5 km from mill
- developing eng for new evaporators (bottleneck)
- installing digester DCS (Fisher-Provox)
- replacing R8 generator reboiler next week (30/130 tubes blocked)
Northwood, Prince George
- installed 8 thou slot barrier screens in A mill, ran very well, attempting to run without quaternary screen; wore them out in 3 weeks in B mill, insufficient capacity, removed while considering next move
- recaust upgrade (green liquor stabilization tank, stacked causticizer, dregs filter, white liquor filter), should start up in near future
Repap, Miramichi
- installing SMC ClO2 generator off gas analyzer
- rebuilding washers E1, D1 upgrade 96, may bypass W35 for wash stage
- rebuilding Solvay design ClO2 plant in 1996,14.5 t/d design, now get 18.5, should get 22 t/d
Repap, Prince Rupert
- on strike
- using enzymes since 1991
- AQ trial was successful
- trying to meet 1 kg/t AOX
- B mill running ECF, trying to get A mill ECF with low Cl2 multiple (.22 to .16, reduced AOX by 50%)
- future - kappa analyzer, screening modifications to handle shives due to ECF bleaching
Stone-Consolidated, Wayagamack
- new bs washers approved, also screen line to reduce BOD load to secondary treatment plant
- proposing to change QPHH bleach plant to ECF ODEoD for 96/97, semibleached pulp
- installed wet scrubber on recovery boiler two months ago
St. Anne-Nackawick
- elcetrostatic precipitator on power boiler in Oct 95
- DCS in evaporator area
- dabbling in AQ and H2O2 (concerned with photoactivity)
- working on $400 million expansion
Tembec, Temiscaming
- purchasing a kappa analyzer
- preliminary O2 delignification stage on one year from now
- pursuing effluent flow reduction plan to reduce load to activated sludge plant
- started construction on weak sulphite liquor storage tank
Weyerhauser, Kamloops
- $100 million expansion including O2 delignification
- also includes debottlenecking, evaporator & recovery work, convert Do to MC, add new brown high density storage with MC discharge
- completion target 1997
- soda ash trial, successful, 100% replacement in Papricycle, 50% in extraction, did it because caustic was not available, cost effective in big mill, but not in small mill because of retention time; not currently using because of supply problems; evaluating cost effectiveness
Weyerhauser, Prince Albert
- approval to spend $11 million to convert R3 to R8/R10 (May/96), and convert Dc stage to dynamic mixers, go from 3% to 4.5 % consistency
- installing MC pump in D2 stage this year
- installing MC pump in E2 stage next year
- permanent retention time measurement system in brown high density for enzymes by Iogen
CXY Chemicals, Vancouver
- expanded Louisiana and other plants, will be one of biggest suppliers in North America
Dupont, Maitland
- double plant capacity at Gibbons, AL , one year behind schedule, complete fall/96
Degussa, Vancouver
- construction started on 5000 mt tankfarm in Quebec City , peroxide to be received from Belgium Jan/96
- 40000 mt to 60000 mt capacity coming on stream in Quebec in 1997, site TBA
FMC, Montreal
- 140 million lbs expansion in Texas H2O2, Jan 97, from 88 million to over 200 million
- Netherlands H2O2 coming on in 1996, for import to Canada
Jack Histed, L’Orignal
- some sw mills in Eastern Canada could benefit from simplified bleaching, some in west too
NLK, Montreal
- TCF study for Cellardennes Belgium - TCF on back burner, ECF for now
- doing study for Mallette, conversion to low odor RB